November 28, 2021
The built-in shelving and seating spelling out “global’ has been installed in the library. In the upcoming weeks, the rest of the shelving will be installed as well.
the new chen family lower school
Meet the Chen Family
project updates
November 20, 2021
Flooring is beginning to be installed in different areas of the building. First to be completed is the upstairs hallway to be used by Grade 3 through Grade 5 students.
November 15, 2021
The globe mural on the outside of the Daneri Family Gymnasium is complete, an exciting addition to the outside of the building.
November 3, 2021
The Daneri Family Gymnasium is now outfitted for basketball, with hoops installed as well as a brand new scoreboard.
September 25, 2021
All classrooms have their own built-in storage, allowing for students to keep their jackets, backpacks, and other items in the classroom with them instead of the hallways.
September 13, 2021
Finishing touches on the parking lot, curbs, ramps and sidewalks have wrapped up, making the school ready and accessible to all visitors.
July 29, 2021
With the installation of the shingles wrapped up, the roofing is now complete. With this benchmark complete, only a few steps remain before the exterior of the school is complete as a whole.
July 17, 2021
One of the most visible benchmarks was completed once the brick and limestone was fully installed around the building. After this, many of the upcoming projects will focus more on internal changes.
July 7, 2021
The base of the parking lot and curbs are complete. While it may not be an addiction to the actual building, it is an important part of the construction process that will be used by many.
May 16, 2021
Exterior wall framing has been completed, creating a stepping stone for future insulation and eventually brick and limestone installation.
May 7, 2021
Now that the interior concrete slabs are finished, we can officially walk around on both stories of the building. Work on the second story can begin, which will house the upgraded library.
April 19, 2021
Two different types of roof decking were completed, for the flat roof over the Daneri Family Gym and for the sloped roofs over the two classroom wings.
March 28, 2021
Two different types of roof decking were completed, for the flat roof over the Daneri Family Gym and for the sloped roofs over the two classroom wings.
March 22, 2021
Steel structure for both classroom wings were completed, giving us a glimpse of what the classrooms will eventually look like as construction progresses.
March 13, 2021
The precast concrete walls housing the multipurpose Lower School Daneri Family Gymnasium and the cafeteria were delivered and erected.
February 24, 2021
As the first batch of structural steel arrived, the Shiel Sexton crew worked to frame the classroom and administration sections, followed by the multipurpose Daneri Family Lower School Gymnasium and cafeteria.
January 29, 2021
Ahead of schedule, masonry crews began work on the 26-foot-tall elevator shaft in the center of the Chen Family Lower School. To work through cold temperatures, a heated tent was installed around the structure.
January 19, 2021
Masonry crews began work on the perimeter foundation for the Daneri Family Lower School Gymnasium. The multipurpose gym is on the north end of the Chen Family Lower School.
December 4, 2020
New sanitary lines for the Chen Family Lower School were connected with existing ones. While not a glamorous step in the construction process, it is a crucial one.
November 20, 2020
The Shiel Sexton crew has already put in 400 man-hours since the start of construction. They completed a Lime Stabilization Process, which reactivates the soil for long-term strength.
November 10, 2020
Land movers and other heavy equipment clear the build site of growth to create a safer work environment for the start of construction.
October 30, 2020
A silt fence was installed to mark the construction boundary, allowing the surrounding campus to be unaffected by the construction process.
October 23, 2020
ISI students, faculty, staff, alumni, and supporters gathered as #OneISI to virtually celebrate the groundbreaking of the new Chen Family Lower School.
October 20, 2020
Construction crews began moving earth in preparation for groundbreaking activities.
October 19, 2020
Crews marked the Chen Family Lower School property for the utilities prior to digging.
September 24, 2020
The City of Indianapolis has released the Improvement Location Permit (ILP) for the construction of the Chen Family Lower School, which officially allows construction to begin.
February 28, 2020
Architects submitted final renders for the Chen Family Lower School, including views of classrooms, the library (shown above), gymnasium, and more. View the renderings slideshow.
December 3, 2019
The architecture team put a 5 step sustainability plan in place, including the use of LED light fixtures and recycled materials, natural daylight in occupied spaces, and rain harvesting.
October 30, 2019
The architecture team revealed early ideas for the palette and texture of the school interior, meant to bring in the character and warmth of the International School.
October 8-9, 2019
Architects captured drone footage of the Michigan Road campus to study traffic flows as they plan the circulation patterns for the Chen Family Lower School.
September 27, 2019
Crews completed soil testing on the site of the new Chen Family Lower School as an important first step in prepping for site construction.
September 17, 2019
The ISI community celebrated the launch of ONE ISI at the annual Wine and Cheese event.
PROject timeline
ONE ISI is a multi-year endeavor* that will create a unified campus by 2022.
2019-2020 Academic Year - public launch of the ONE ISI campaign
2020-2021 Academic Year - Chen Family Lower School construction start
2021-2022 Academic Year - Construction and preview tours
August 2022 - Grand opening